About the Project
It takes 4 to 4-1/2 months to build a 3 or 4 bedroom one-story home of 1,100 to 1,400 square feet. Each home is equipped with the following:
- ADT Security System
- Concrete driveway
- Front porch and back porch/patio
- Refrigerator, stove, furnace, hot water heater, full bath
- One storm/screen door
- Choice of color for siding, trim, carpet and vinyl flooring
- Mailbox
- Temporary fence at rear of backyard
Typical Construction Plan
The following table lists typical construction tasks by week. Construction work is subject to change due to a variety of factors. Patience and flexibility on the part of sponsor volunteers is appreciated, and helps the tasks flow smoothly.
| Week | Tasks |
| 1 |
Install concrete footings and underdrainage (moderate to heavy lifting)
|
| 2 |
Install concrete blocks for foundation ( heavy lifting)
|
| 3 |
Install concrete blocks, sealing blocks and backfill (some moderate to heavy lifting)
|
| 4 |
Build first floor deck and walls
|
| 5 |
Erect roof trusses, install roof sheathing (moderate to heavy lifting)
|
| 6 |
Complete roofing
|
| 7 |
Build porches, install windows and doors
|
| 8 |
Rough-in heating, electrical, and plumbing
|
| 9 |
Install siding and gutters
|
| 10 |
Install insulation |
| 11 |
Hang and finish drywall |
| 12 |
Hang and finish drywall |
| 13 |
Sand, prep and prime drywall, install trim, finish painting |
| 14 |
Finish heating, electrical and plumbing; install carpet and flooring |
| 15 |
Landscaping |
|